[2017] FWCFB 651

The attached document replaces the document previously issued with the above code on 31 January 2017.

Endnotes 10 and 15 are amended.

Associate to Vice President Catanzariti

Dated 1 February 2017

[2017] FWCFB 651
FAIR WORK COMMISSION

DECISION


Fair Work Act 2009

s.604 - Appeal of decisions

United Voice - Queensland Branch
v
MSS Security Pty Limited T/A MSS Security Pty Limited
(C2015/3752)

VICE PRESIDENT CATANZARITI
SENIOR DEPUTY PRESIDENT DRAKE
COMMISSIONER SPENCER

SYDNEY, 31 JANUARY 2017

Appeal against decision [2015] FWCA 1559 of Commissioner Gregory at Melbourne on 9 April 2015 in matter number AG2014/10202.

[1] On 9 April 2015, Commissioner Gregory issued a Decision 1 which approved the MSS Security QLD Enterprise Agreement 2014-2018 (Agreement) with an undertaking. On 30 April 2015, United Voice (Appellant) lodged a Notice of Appeal appealing the Commissioner’s Decision. The Appellant and MSS Security (Respondent) are covered by the Security Services Industry Award 2010 (Award) and at the heart of the appeal was whether employees of the Respondent were better off under the Award or the Agreement.

[2] We heard the appeal and, on 12 November 2015, issued a decision (First Quashed Decision) which granted permission to appeal, upheld the appeal, and concluded that the Agreement would be approved with an amended undertaking. 2 On 1 December 2015, Vice President Catanzariti issued a decision (Second Quashed Decision) which recorded that Commissioner Gregory’s Decision had been set aside and, that the Agreement, with the new undertaking, is approved.

[3] On 23 August 2016, a Full Court of the Federal Court of Australia quashed both the First Quashed Decision and the Second Quashed Decision. 3 The Full Court of the Federal Court of Australia issued a writ of mandamus requiring us to rehear and decide the union’s appeal according to law.4 As such, we heard the matter on 5 December 2016. We informed the parties that our decision would be published in due course.

[4] At the hearing on 5 December 2016, Mr W. Friend of Queen’s Counsel and Mr R. Reed of Counsel sought permission to appear for the Appellant. Mr M. Follett of Counsel sought permission to appear for the Respondent. Given the complexity of the matter, and having regard to s.596 of the Fair Work Act 2009 (the Act), permission was granted to both parties to be represented. 5

Permission to Appeal

[5] The FWC will grant permission to appeal only if it is in the public interest to do so. 6 The test of assessing whether a matter is in the public interest is discretionary and involves a broad value judgement.7 In GlaxoSmithKline Australia Pty Ltd v Colin Makin,8 the Full Bench summarised the test for determining the public interest as follows:

[6] Alternately, the second ground for granting permission to appeal is that the decision is attended with sufficient doubt to warrant its reconsideration or that substantial injustice may result if leave is refused. 9

[7] In determining whether permission to appeal should be granted we have reviewed and considered all material filed by the parties including all submissions, correspondence and relevant authorities.

[8] We find that permission to appeal should be granted in this matter. We are of the view that the appeal raises important questions concerning the application of the BOOT in circumstances where the Commissioner’s discretion to determine whether employees were better off under the Agreement is an issue in the dispute. We consider this to be an important matter regarding the Commissioner’s approach in making such a determination and, therefore, the dispute arising in this case is a matter of public interest. It is on this basis that permission to appeal is granted.

The Appeal

[9] At the heart of the dispute was whether the Commissioner erred by accepting that the Agreement passed the better off overall test (BOOT).

Appellant’s Submissions

[10] Firstly, the Appellant submitted that the application of the BOOT required the Commissioner to conduct an assessment of the Agreement, determine which clauses were more and less beneficial than the Award, and then make an overall assessment of whether an employee would be better off under the Agreement. 10

[11] The Appellant contended that when clause 21.1 (the ordinary hours provision) and clause 23.3 (the overtime provision) are read together, it is apparent that hours in excess of 304 hours over an 8 week roster cycle are to be treated as overtime under the Award and are to be paid at the differential rates set out in clause 23.3. That is, it cannot be said that an employee is working overtime until he or she has worked more than 304 hours during the 8 week cycle. The Appellant noted that, pursuant to clause 4.3.5 of the Agreement, overtime hours would be notionally assigned to Sunday work, regardless of when in the roster those hours fell. Therefore, as overtime was notionally worked on a Sunday, no additional penalty over that which applied to Sunday work would be payable. In this regard, the Appellant noted that a maximum of 12 hours overtime could be attributed to Sunday work.

[12] The Appellant posited that, under the Award, overtime is payable when the maximum number of ordinary hours in the roster cycle (304 hours over 8 weeks) has been worked. However, by shifting those hours from the end of the roster to Sundays earlier in the roster, the Agreement reduces the number of overtime hours for which a loading would be payable. Therefore, non-aggregated wage employees working the 8 week roster cycle would suffer a significant diminution in entitlement as a result of the operation of clause 4.3.5(a) of the Agreement. In this regard, the Appellant asserted that the difference between ordinary time pay rates in the Agreement and the Award were so small as not to offset for the loss of overtime entitlements.

[13] Therefore, the Appellant contended that the Commissioner erred in failing to appreciate the effect of clause 4.3.5(a) of the Agreement and argued that he should not have been satisfied that the Agreement passed the BOOT. In particular, the Appellant asserted that the Commissioner erred in relying on the decision of Harland & Ors v MSS Security 11 (“Harland”) as authority for the proposition that the Award allowed the Respondent to construct its roster in the same way as that provided for in clause 4.3.5 of the Agreement.

[14] The Appellant contended that the Commissioner erred in relying on Harland as the facts before Commissioner Williams in Harland and Commissioner Gregory were entirely different. The Appellant highlighted the following distinguishing features between the cases:

[15] Secondly, the Appellant contended that the Commissioner erred by approving the Agreement while it contained clause 4.3.6 and in accepting the undertakings offered by the Respondent. The Appellant noted that clause 4.3.6 is a “voluntary overtime” provision, which allows permanent employees, by written agreement, to work overtime at casual rates of 125%. 12 The Appellant asserted that the voluntary overtime rates in clause 4.3.6 were inferior to the overtime rates in the Award.13 The Appellant highlighted that section 190 of the Act allows the Commission to approve an enterprise agreement with undertakings. In this regard, the Appellant posited that the section only applies if the Commission has a concern that the agreement does not meet the requirements set out in sections 186 and 187 (the BOOT). The Appellant contended, therefore, that a concern was evidently held by the Commissioner in light of the submissions by the Respondent14.

[16] The Appellant contended that, in approving the Agreement, the Commissioner accepted undertakings from the Respondent for quarterly audits of employees who worked voluntary overtime under clause 4.3.6 in excess of minimal amounts per quarter, with a payment within 7 days of the end of the quarter of any shortfall in wage payments to the employee, compared with amounts which would have been paid under the Award.

[17] The Appellant asserted that the Commissioner erred in accepting the above undertakings offered by the Respondent for the following reasons:

Respondent’s Submissions

[18] The Respondent addressed each of the grounds of appeal outlined by the Appellant.

[19] In relation to the first ground of appeal, the Respondent contended that the combined effect of clauses 4.3.1 and 4.3.5 is that the Respondent is permitted to allocate and roster any overtime worked within an 8 week roster cycle on a Sunday. 16 In this regard, the Respondent disputed the Appellant’s contention that overtime cannot be allocated to a specific day within the rotating roster in this manner and, therefore, does not pass the BOOT. The Respondent asserted that this argument was put before the Commissioner and the Full Bench and was rejected, and likewise, the argument should be rejected in this appeal.

[20] The Respondent submitted that within an 8 week cycle, maximum ordinary hours under the Award are 304 hours. In this regard, under the Award, overtime is payable for any additional hours worked within that cycle, which is exactly the same position under the Agreement.

[21] The Respondent noted that the factual scenario in question related to employees of the Respondent who performed 336 rostered hours within an 8 week cycle made up of 12 hour shifts on a “four days on, four days off” pattern. The Respondent highlighted that the Appellant relies on two foundational premises:

[22] Following on from these premises, the Respondent submitted that the Appellant asserted that allocating more than 12 hours of overtime to a Sunday under the Agreement disadvantages employees by eliminating other overtime penalties that would otherwise apply.

[23] The Respondent contended that if the two premises outlined above were correct, there may be a theoretical disadvantage to these employees if the Respondent chose to allocate overtime to Sundays as permitted by clause 4.3.5(a) of the Agreement. However, the Respondent asserted that neither of the above premises are correct and, therefore, the provisions do not trigger any BOOT concerns.

[24] The Respondent submitted that no provision of the Award determines how or when the “averaged” 304 hours are to be worked within that 8 week cycle roster. Further, the Respondent asserted that no provision of the Award prohibits or prevents an employer allocating overtime within the 8 week roster on any day it sees fit. 17 On this basis, the Respondent contended that, having regard to the factual scenario above, no provision of the Award necessitates that only the last 32 hours worked in the 8 week roster cycle must be regarded as overtime and allocated (and paid) as such. Therefore, the Respondent asserted that, provided the employer allocates and pays for 32 hours of overtime within the 8 week roster cycle, the requirements of the Award are fully met.

[25] In relation to the second ground of appeal, the Respondent addressed each of the four reasons outlined by the Appellant in contending that the Commissioner erred in accepting the undertakings offered by the Respondent.

[26] Regarding the first reason outlined by the Appellant, the Respondent asserted that the need for an undertaking arises where a “concern” exists as to the approval requirements (section 190(1)(b) of the Act), not that the Agreement did not pass the BOOT. Further, and in any event, the Respondent submitted that the purpose of the undertaking is to resolve the BOOT issue.

[27] Regarding the second reason outlined by the Appellant, the Respondent noted that, to the extent that the Full Bench concluded that this manifested an appellable error, that error remains.

[28] Regarding the third reason outlined by the Appellant, the Respondent contended that this reason was misconceived and that the full amounts required to be paid by the Agreement, including all amounts due under clause 4.3.6, would be paid in full fortnightly. 18

[29] Regarding the fourth reason, the Respondent contended that this was an assertion without foundation and it was not identified how or why such a proposition is so.

[30] Based on the above, the Respondent submitted that the Commission should, pursuant to 607(3)(b) of the Act, rehear the application to approve the Agreement, give consideration to the statutory requirements for approval and, if satisfied that the Agreement should be approved, provide sufficient reasons for reaching that state of satisfaction and approve the Agreement.

Consideration

[31] We note that a decision under appeal is of a discretionary nature and such a decision can only be successfully challenged on appeal if it is shown that the discretion was not exercised correctly. We note that it is not open for us to substitute our view on the matters that fell for determination before the Commissioner in the absence of error of an appellable nature in the Commissioner’s original Decision. As the High Court said in House v The King 19:

[32] A key consideration as to whether the Commission can approve an agreement is a determination that the agreement passes the “better off overall test”. That requirement is set out at s 186(2)(d) of the Act. The definition of the BOOT is set out at s 193(1) as follows:

[33] As Vice President Lawler observed in NTEU v UNSW:

[34] Clause 21.1 of the Award prescribes that hours in excess of 304 hours over an eight week roster are treated as overtime. Clause 23.3 of the Award prescribes that when an employee works overtime, the employer must pay the employee the ordinary time rate for the period of overtime together with the following loadings:

For overtime worked on

Loading in addition to ordinary time

Monday to Friday – first 2 hours

50%

Monday to Friday – thereafter

100%

Saturday – first 2 hours

50%

Saturday – thereafter

100%

Sunday

100%

Public Holiday

150%

[35] By comparison, clause 4.3.5(a) of the Agreement provides that overtime in a 12-hour rotating roster cycle will generally be allocated to hours that fall on a Sunday: at the end of a Saturday and a Sunday day shift. The effect of clause 4.3.5 of the Agreement is that over the period of the roster, the overtime hours are assigned to Sunday work, regardless of when in the roster those hours actually fell. Therefore, no additional penalty over that which applied to Sunday work would be payable.

[36] Pursuant to the Award, overtime is payable when the hours in excess of the maximum have been worked. By shifting those hours from the end of the roster, to Sundays earlier in the roster, the Agreement reduced the number of overtime hours for which loading would be payable. We are of the view that this is disadvantageous to the non-aggregated wage employees of the Respondent when compared to what these employees are offered under the Award. It follows that non-aggregated wage employees are better off under clause 21.1 and 23.3 of the Award than under clause 4.3.5 of the Agreement.

[37] Clause 4.3.6 of the Agreement provides that permanent employees are allowed, by written agreement, to work overtime at casual rates of 125%. Clause 4.3.6(b) caps the overtime to be worked at 24 hours per fortnight. These clauses are inferior to the clauses in the Award, which prescribe higher overtime rates. In this regard too, it follows that certain employees are better off under the Award than the Agreement. In light of this disadvantage, Commissioner Gregory accepted undertakings from the Respondent for quarterly audits of non-aggregated wage employees who worked overtime with a payment within 7 days of any shortfall in wage payments to the employee compared with amounts which would have been paid under the Award.

[38] In our view, this undertaking would cause an employee who is worse off under the Agreement to wait up to three months to be properly remunerated for work performed. This is inconsistent with section 190(3)(a) of the Act which prescribes that:

[39] In light of the above, we are of the view that the undertakings did not satisfy the requirement prescribed by section 190(3)(a) of the Act. Further, the undertakings contrive section 323 of the Act, which require that employees are remunerated at least monthly.

[40] The Appellant has tendered an undertaking in which it undertakes to conduct monthly audits of employees who have worked overtime. In our previous decision 21 that the Full Court of the Federal Court quashed, we stated that by amending the undertaking from quarterly to monthly reviews, the undertaking would be satisfactory.22

[41] However, following the quashing of our decision and the comments of the Full Court of the Federal Court, we have reconsidered the appeal before us. In doing so, we have considered all material filed by the parties including all submissions, correspondence and relevant authorities.

[42] Having reconsidered the material before us, we are of the view that while monthly audits are preferable to quarterly audits, a one month delay in remuneration does not remedy the contravention of section 190(1) that resulted from the original three month delay. Whether the delay is one month or three months, the employees are financially disadvantaged under the Agreement as there is a delay in the payment of the remuneration that they are, under the Award, entitled to. While the Respondent’s undertaking, which reduces the timing of the audits to one month, is preferable to quarterly audits, we are not satisfied that these undertakings make employees better off under the Agreement.

[43] At PN51 – PN52 of the Transcript we put this to the Respondent. The Respondent asserted that it is only “potentially” to the detriment of employees to have to wait one month to receive their remuneration. We disagree with this assertion and are of the view that it is to the detriment of the employees to have to wait one month to receive their remuneration and that, as a result, the employees are not better off under the Agreement and undertaking.

[44] The Respondent submitted that five provisions of the Agreement are more beneficial to employees when compared to provisions of the Award. 23 In our view, these benefits should be taken into account. However, we agree with the Appellant to the extent that it submits that the benefits that the Respondent points to do not off-set the detrimental impact caused by the loss of overtime entitlements.

[45] We are not satisfied that there are other clauses of the Agreement that off-set the loss of overtime entitlements, or other beneficial clauses which result in non-aggregated wage employees being better off overall under the Agreement. We are, therefore, not satisfied that, pursuant to an overall assessment of the Agreement, the BOOT has been satisfied.

[46] In light of the above, we are of the view that the Agreement does not satisfy the BOOT and that this is not rectified by the undertakings. We are of the view that there are appealable errors in accordance with House v The King in the two grounds of appeal as submitted by the Appellant. We are of the view that the Commissioner erred in approving the Agreement. As such, we are of the view that the Commissioner did not properly exercise the discretion which is vested in the Commission. We are, therefore, satisfied that the appeal must be upheld and that we should quash the original Decision. As such, the Commissioner’s Decision is quashed and the Agreement is not approved.

Conclusion

[47] Permission to appeal is granted.

[48] The appeal is upheld.

[49] Commissioner Gregory’s Decision 24 is quashed.

[50] The Agreement is not approved.

Seal of the Fair Work Commission with member's signature
VICE PRESIDENT

Appearances:

Mr W. Friend of Queen’s Counsel and Mr R. Reed of Counsel for the Appellant

Mr M. Follett of Counsel for the Respondent

Hearing details:

5 December

2016

Sydney

 1   [2015] FWCA 1559.

 2   [2015] FWCFB 6923.

 3   United Voice v MSS Security Pty Ltd [2016] FCAFC 124.

 4   Ibid, paragraph [21].

 5   Transcript, PN5.

 6   Fair Work Act 2009 (Cth) s 604(2).

 7   Esso Australia Pty Ltd v AMWU; CEPU; AWU [2015] FWCFB 210 at [6].

 8   [2010] FWAFB 5343 at [27].

 9   Esso Australia Pty Ltd v AMWU; CEPU; AWU [2015] FWCFB 210 at [7].

 10   Armacell Australia Pty Ltd (2010) 202 IR 38; [2010] FWAFB 9985 at [41]; Hart v Coles Supermarkets Pty Ltd & Anor [2016] FWCFB 2887, [6].

 11   [2013] FWC 8064, [74], [76]-[78].

 12   Appeal Book, p 130.

 13   Appellant’s Submissions, Appendix B; Appeal Book, p 154.

 14   MSS Security’s Submissions in AG2014/10202, [25]-[26]; Appeal Book, pp 22-23.

 15   Hart v Coles Supermarkets Australia Pty Ltd & Anor [2016] FWCFB 2887, [34].

 16   Agreement, clause 4.3.5(a).

 17   Harland v MSS Security Pty Ltd [2013] FWC 8064, [77]-[78]; Award, cl 21.1(a).

 18   Agreement, cl 3.1.3.

 19   [1936] HCA 40.

 20   [2010] FWAA 9588.

 21   [2015] FWCFB 6923.

 22   [2015] FWCFB 6923, [58].

 23   Transcript, PN78.

 24   [2015] FWCA 1559.

Printed by authority of the Commonwealth Government Printer

<Price code C, PR589862>