MA000015 PR729269 |
FAIR WORK COMMISSION |
DETERMINATION |
Fair Work Act 2009
s.285—Annual wage review
Annual Wage Review 2020–21
(C2021/1)
RAIL INDUSTRY AWARD 2020
[MA000015]
Rail industry | |
JUSTICE ROSS, PRESIDENT |
MELBOURNE, 25 JUNE 2021 |
Annual Wage Review 2020–21.
A. Further to the decision issued by the Expert Panel in the Annual Wage Review
2020–21 on 16 June 2021 [[2021] FWCFB 3500], the above award is varied as follows:
1. By deleting the table appearing in clause 15.1(a) and inserting the following:
Classification |
Annual salary equivalent1 |
Minimum weekly rate |
Minimum hourly rate |
$ |
$ |
$ | |
Level 1 Rail Worker (CAP) |
42,490 |
814.50 |
21.43 |
Level 2 Rail Worker (CAP) |
46,027 |
882.30 |
23.22 |
Level 3 Rail Worker (CAP) |
47,795 |
916.20 |
24.11 |
Level 4 Rail Worker (CAP) |
49,913 |
956.80 |
25.18 |
Level 5 Rail Worker (CAP) |
54,159 |
1038.20 |
27.32 |
Level 6 Rail Worker (CAP) |
58,051 |
1112.80 |
29.28 |
Level 7 Rail Worker (CAP) |
61,588 |
1180.60 |
31.07 |
Level 8 Rail Worker (CAP) |
69,361 |
1329.60 |
34.99 |
Level 9 Rail Worker (CAP) |
83,154 |
1594.00 |
41.95 |
2. By deleting the table appearing in clause 15.1(b) and inserting the following:
Classification |
Annual salary equivalent1 |
Minimum weekly rate |
Minimum hourly rate |
$ |
$ |
$ | |
Level 1 Rail Worker (Op) |
40,304 |
772.60 |
20.33 |
Level 2 Rail Worker (Op) |
42,850 |
821.40 |
21.62 |
Level 3 Rail Worker (Op) |
47,451 |
909.60 |
23.94 |
Level 4 Rail Worker (Op) |
52,047 |
997.70 |
26.26 |
Level 5 Rail Worker (Op) |
56,992 |
1092.50 |
28.75 |
Level 6 Rail Worker (Op) |
60,925 |
1167.90 |
30.73 |
3. By deleting the table appearing in clause 15.1(c) and inserting the following:
Classification |
Annual salary equivalent1 |
Minimum weekly rate |
Minimum hourly rate |
$ |
$ |
$ | |
Level 1 Rail Worker (TCI) |
41,441 |
794.40 |
20.91 |
Level 2 Rail Worker (TCI) |
43,043 |
825.10 |
21.71 |
Level 3 Rail Worker (TCI) |
44,524 |
853.50 |
22.46 |
Level 4 Rail Worker (TCI) |
46,924 |
899.50 |
23.67 |
Level 5 Rail Worker (TCI) |
49,011 |
939.50 |
24.72 |
Level 6 Rail Worker (TCI) |
51,191 |
981.30 |
25.82 |
Level 7 Rail Worker (TCI) |
55,229 |
1058.70 |
27.86 |
4. By deleting the words “1 November 2020” in clause 15.7(b) and inserting “1 July 2021”.
5. By deleting the amount “$16.67” appearing in clause 18.2(a) and inserting “$17.09”.
6. By deleting the amounts “$11.41” and “$28.61” appearing in clause 18.2(b)(i) and inserting “$11.69” and “$29.33” respectively.
7. By deleting the amount “$0.67” appearing in clause 18.3(d)(i) and inserting “$0.69”.
8. By deleting the amount “$0.88” appearing in clause 18.3(e) and inserting “$0.90”.
9. By deleting the amount “$0.67” appearing in clause 18.3(f) and inserting “$0.69”.
10. By deleting the amount “$0.48” appearing in clause 18.3(g) and inserting “$0.50”.
11. By deleting the amount “$0.88” appearing in clause 18.3(h) and inserting “$0.90”.
12. By deleting the amount “$1.73” appearing in clause 18.3(i) and inserting “$1.78”.
13. By deleting the amount “$0.51” appearing in clause 18.3(j)(i) and inserting “$0.52”.
14. By deleting the amount “$3.06” appearing in clause 21.2(a) and inserting “$3.13”.
15. By deleting the amount “$3.63” appearing in clause 21.2(b) and inserting “$3.72”.
16. By deleting the amount “$6.89” appearing in clause 21.2(c) and inserting “$7.07”.
17. By deleting the table appearing in clause B.1.3 and inserting the following:
|
Ordinary hours |
Early morning/ afternoon |
Night |
Permanent night |
Saturday |
Sunday |
Public holiday |
% of ordinary hourly rate1 | |||||||
|
100% |
100% + $3.13 |
100% + $3.72 |
100% + $7.07 |
150% |
200% |
250% |
$ |
$ |
$ |
$ |
$ |
$ |
$ | |
Level 1 Rail Worker (CAP) |
21.43 |
24.56 |
25.15 |
28.50 |
32.15 |
42.86 |
53.58 |
Level 2 Rail Worker (CAP) |
23.22 |
26.35 |
26.94 |
30.29 |
34.83 |
46.44 |
58.05 |
Level 3 Rail Worker (CAP) |
24.11 |
27.24 |
27.83 |
31.18 |
36.17 |
48.22 |
60.28 |
Level 4 Rail Worker (CAP) |
25.18 |
28.31 |
28.90 |
32.25 |
37.77 |
50.36 |
62.95 |
Level 5 Rail Worker (CAP) |
27.32 |
30.45 |
31.04 |
34.39 |
40.98 |
54.64 |
68.30 |
Level 6 Rail Worker (CAP) |
29.28 |
32.41 |
33.00 |
36.35 |
43.92 |
58.56 |
73.20 |
Level 7 Rail Worker (CAP) |
31.07 |
34.20 |
34.79 |
38.14 |
46.61 |
62.14 |
77.68 |
Level 8 Rail Worker (CAP) |
34.99 |
38.12 |
38.71 |
42.06 |
52.49 |
69.98 |
87.48 |
Level 9 Rail Worker (CAP) |
41.95 |
45.08 |
45.67 |
49.02 |
62.93 |
83.90 |
104.88 |
18. By deleting the table appearing in clause B.1.4 and inserting the following:
|
Weekday – first 3 hours |
Weekday – after 3 hours |
Saturday |
Sunday – all day |
Public holiday |
% of ordinary hourly rate1 | |||||
150% |
200% |
150% |
200% |
250% | |
$ |
$ |
$ |
$ |
$ | |
Level 1 Rail Worker (CAP) |
32.15 |
42.86 |
32.15 |
42.86 |
53.58 |
Level 2 Rail Worker (CAP) |
34.83 |
46.44 |
34.83 |
46.44 |
58.05 |
Level 3 Rail Worker (CAP) |
36.17 |
48.22 |
36.17 |
48.22 |
60.28 |
Level 4 Rail Worker (CAP) |
37.77 |
50.36 |
37.77 |
50.36 |
62.95 |
Level 5 Rail Worker (CAP) |
40.98 |
54.64 |
40.98 |
54.64 |
68.30 |
Level 6 Rail Worker (CAP) |
43.92 |
58.56 |
43.92 |
58.56 |
73.20 |
Level 7 Rail Worker (CAP)2 |
– |
– |
– |
– |
– |
Level 8 Rail Worker (CAP)2 |
– |
– |
– |
– |
– |
Level 9 Rail Worker (CAP)2 |
– |
– |
– |
– |
– |
19. By deleting the table appearing in clause B.1.5 and inserting the following:
|
Ordinary hours |
Early morning/ afternoon |
Night |
Permanent night |
Saturday |
Sunday |
Public holiday |
% of ordinary hourly rate1 | |||||||
|
100% |
100% + $3.13 |
100% + $3.72 |
100% + $7.07 |
150% |
200% |
250% |
$ |
$ |
$ |
$ |
$ |
$ |
$ | |
Level 1 Rail Worker (TCI) |
20.91 |
24.04 |
24.63 |
27.98 |
31.37 |
41.82 |
52.28 |
Level 2 Rail Worker (TCI) |
21.71 |
24.84 |
25.43 |
28.78 |
32.57 |
43.42 |
54.28 |
Level 3 Rail Worker (TCI) |
22.46 |
25.59 |
26.18 |
29.53 |
33.69 |
44.92 |
56.15 |
Level 4 Rail Worker (TCI) |
23.67 |
26.80 |
27.39 |
30.74 |
35.51 |
47.34 |
59.18 |
Level 5 Rail Worker (TCI) |
24.72 |
27.85 |
28.44 |
31.79 |
37.08 |
49.44 |
61.80 |
Level 6 Rail Worker (TCI) |
25.82 |
28.95 |
29.54 |
32.89 |
38.73 |
51.64 |
64.55 |
Level 7 Rail Worker (TCI) |
27.86 |
30.99 |
31.58 |
34.93 |
41.79 |
55.72 |
69.65 |
20. By deleting the table appearing in clause B.1.6 and inserting the following:
|
Weekday – first 3 hours |
Weekday – after 3 hours |
Saturday |
Sunday – all day |
Public holiday |
% of ordinary hourly rate1 | |||||
150% |
200% |
150% |
200% |
250% | |
$ |
$ |
$ |
$ |
$ | |
Level 1 Rail Worker (TCI) |
31.37 |
41.82 |
31.37 |
41.82 |
52.28 |
Level 2 Rail Worker (TCI) |
32.57 |
43.42 |
32.57 |
43.42 |
54.28 |
Level 3 Rail Worker (TCI) |
33.69 |
44.92 |
33.69 |
44.92 |
56.15 |
Level 4 Rail Worker (TCI) |
35.51 |
47.34 |
35.51 |
47.34 |
59.18 |
Level 5 Rail Worker (TCI) |
37.08 |
49.44 |
37.08 |
49.44 |
61.80 |
Level 6 Rail Worker (TCI) |
38.73 |
51.64 |
38.73 |
51.64 |
64.55 |
Level 7 Rail Worker (TCI) |
41.79 |
55.72 |
41.79 |
55.72 |
69.65 |
21. By deleting the table appearing in clause B.1.7 and inserting the following:
Ordinary hours |
Early morning/ afternoon |
Night |
Permanent night |
Saturday |
Sunday |
Public holiday | |
% of ordinary hourly rate1 | |||||||
100% |
100% + $3.13 |
100% + $3.72 |
100% + $7.07 |
150% |
200% |
250% | |
$ |
$ |
$ |
$ |
$ |
$ |
$ | |
Level 1 Rail Worker (Op) |
20.33 |
23.46 |
24.05 |
27.40 |
30.50 |
40.66 |
50.83 |
Level 2 Rail Worker (Op) |
21.62 |
24.75 |
25.34 |
28.69 |
32.43 |
43.24 |
54.05 |
Level 3 Rail Worker (Op) |
23.94 |
27.07 |
27.66 |
31.01 |
35.91 |
47.88 |
59.85 |
Level 4 Rail Worker (Op) |
26.26 |
29.39 |
29.98 |
33.33 |
39.39 |
52.52 |
65.65 |
Level 5 Rail Worker (Op) |
28.75 |
31.88 |
32.47 |
35.82 |
43.13 |
57.50 |
71.88 |
Level 6 Rail Worker (Op) |
30.73 |
33.86 |
34.45 |
37.80 |
46.10 |
61.46 |
76.83 |
22. By deleting the table appearing in clause B.1.8 and inserting the following:
Weekday – first 3 hours |
Weekday – after 3 hours |
Saturday |
Sunday – all day |
Public holiday | |
% of ordinary hourly rate1 | |||||
150% |
200% |
150% |
200% |
250% | |
$ |
$ |
$ |
$ |
$ | |
Level 1 Rail Worker (Op) |
30.50 |
40.66 |
30.50 |
40.66 |
50.83 |
Level 2 Rail Worker (Op) |
32.43 |
43.24 |
32.43 |
43.24 |
54.05 |
Level 3 Rail Worker (Op) |
35.91 |
47.88 |
35.91 |
47.88 |
59.85 |
Level 4 Rail Worker (Op) |
39.39 |
52.52 |
39.39 |
52.52 |
65.65 |
Level 5 Rail Worker (Op) |
43.13 |
57.50 |
43.13 |
57.50 |
71.88 |
Level 6 Rail Worker (Op) |
46.10 |
61.46 |
46.10 |
61.46 |
76.83 |
23. By deleting the table appearing in clause B.2.1 and inserting the following:
|
Ordinary hours |
Early morning/ afternoon |
Night |
Permanent night |
Saturday |
Sunday |
Public holiday |
% of ordinary hourly rate1 | |||||||
125% |
125% + $3.13 |
125% + $3.72 |
125% + $7.07 |
175% |
225% |
275% | |
$ |
$ |
$ |
$ |
$ |
$ |
$ | |
Level 1 Rail Worker (CAP) |
26.79 |
29.92 |
30.51 |
33.86 |
37.50 |
48.22 |
58.93 |
Level 2 Rail Worker (CAP) |
29.03 |
32.16 |
32.75 |
36.10 |
40.64 |
52.25 |
63.86 |
Level 3 Rail Worker (CAP) |
30.14 |
33.27 |
33.86 |
37.21 |
42.19 |
54.25 |
66.30 |
Level 4 Rail Worker (CAP) |
31.48 |
34.61 |
35.20 |
38.55 |
44.07 |
56.66 |
69.25 |
Level 5 Rail Worker (CAP) |
34.15 |
37.28 |
37.87 |
41.22 |
47.81 |
61.47 |
75.13 |
Level 6 Rail Worker (CAP) |
36.60 |
39.73 |
40.32 |
43.67 |
51.24 |
65.88 |
80.52 |
Level 7 Rail Worker (CAP) |
38.84 |
41.97 |
42.56 |
45.91 |
54.37 |
69.91 |
85.44 |
Level 8 Rail Worker (CAP) |
43.74 |
46.87 |
47.46 |
50.81 |
61.23 |
78.73 |
96.22 |
Level 9 Rail Worker (CAP) |
52.44 |
55.57 |
56.16 |
59.51 |
73.41 |
94.39 |
115.36 |
24. By deleting the table appearing in clause B.2.2 and inserting the following:
|
Ordinary hours |
Early morning/ afternoon |
Night |
Permanent night |
Saturday |
Sunday |
Public holiday |
% of ordinary hourly rate1 | |||||||
125% |
125% + $3.13 |
125% + $3.72 |
125% + $7.07 |
175% |
225% |
275% | |
$ |
$ |
$ |
$ |
$ |
$ |
$ | |
Level 1 Rail Worker (TCI) |
26.14 |
29.27 |
29.86 |
33.21 |
36.59 |
47.05 |
57.50 |
Level 2 Rail Worker (TCI) |
27.14 |
30.27 |
30.86 |
34.21 |
37.99 |
48.85 |
59.70 |
Level 3 Rail Worker (TCI) |
28.08 |
31.21 |
31.80 |
35.15 |
39.31 |
50.54 |
61.77 |
Level 4 Rail Worker (TCI) |
29.59 |
32.72 |
33.31 |
36.66 |
41.42 |
53.26 |
65.09 |
Level 5 Rail Worker (TCI) |
30.90 |
34.03 |
34.62 |
37.97 |
43.26 |
55.62 |
67.98 |
Level 6 Rail Worker (TCI) |
32.28 |
35.41 |
36.00 |
39.35 |
45.19 |
58.10 |
71.01 |
Level 7 Rail Worker (TCI) |
34.83 |
37.96 |
38.55 |
41.90 |
48.76 |
62.69 |
76.62 |
25. By deleting the table appearing in clause B.2.3 and inserting the following:
|
Ordinary hours |
Early morning/ afternoon |
Night |
Permanent night |
Saturday |
Sunday |
Public holiday |
% of ordinary hourly rate1 | |||||||
125% |
125% + $3.13 |
125% + $3.72 |
125% + $7.07 |
175% |
225% |
275% | |
$ |
$ |
$ |
$ |
$ |
$ |
$ | |
Level 1 Rail Worker (Op) |
25.41 |
28.54 |
29.13 |
32.48 |
35.58 |
45.74 |
55.91 |
Level 2 Rail Worker (Op) |
27.03 |
30.16 |
30.75 |
34.10 |
37.84 |
48.65 |
59.46 |
Level 3 Rail Worker (Op) |
29.93 |
33.06 |
33.65 |
37.00 |
41.90 |
53.87 |
65.84 |
Level 4 Rail Worker (Op) |
32.83 |
35.96 |
36.55 |
39.90 |
45.96 |
59.09 |
72.22 |
Level 5 Rail Worker (Op) |
35.94 |
39.07 |
39.66 |
43.01 |
50.31 |
64.69 |
79.06 |
Level 6 Rail Worker (Op) |
38.41 |
41.54 |
42.13 |
45.48 |
53.78 |
69.14 |
84.51 |
25. By deleting the amount “$23.09” appearing in clause C.1.1 and inserting “$23.67”.
26. By deleting the table appearing in clause C.1.1 and inserting the following:
Allowance |
Clause |
% of standard rate |
$ |
Payable |
First aid allowance |
18.2(a) |
72.2 |
17.09 |
per week |
On-call allowance: For a night |
18.2(b)(i) |
49.4 |
11.69 |
per night |
On-call allowance: For a day and night |
18.2(b)(i) |
123.9 |
29.33 |
per day and night |
Wet places |
18.3(d)(i) |
2.9 |
0.69 |
per hour |
Confined spaces |
18.3(e) |
3.8 |
0.90 |
per hour |
Dirty work |
18.3(f) |
2.9 |
0.69 |
per hour |
Height money |
18.3(g) |
2.1 |
0.50 |
per hour |
Insulation materials |
18.3(h) |
3.8 |
0.90 |
per hour |
Explosive powered tools—per day |
18.3(i) |
7.5 |
1.78 |
per day |
Explosive powered tools—per hour |
18.3(i) |
Per day divided by 7.6 |
0.23 |
per hour |
Foundry allowance |
18.3(j)(i) |
2.2 |
0.52 |
per hour |
Early morning or afternoon shift |
21.2(a) |
13.24 |
3.13 |
per hour |
Night shift |
21.2(b) |
15.73 |
3.72 |
per hour |
Permanent night shift |
21.2(c) |
29.86 |
7.07 |
per hour |
B. This determination comes into operation on 1 July 2021. In accordance with s.286(5) of the Fair Work Act 2009 this determination does not take effect in relation to a particular employee until the start of the employee’s first full pay period that starts on or after 1 July 2021.
PRESIDENT
Printed by authority of the Commonwealth Government Printer