MA000020  PR718992
FAIR WORK COMMISSION

DETERMINATION


Fair Work Act 2009

s.157—variation of modern award

Expense-related allowances 2020
(AM2020/19)

BUILDING AND CONSTRUCTION GENERAL ON-SITE AWARD 2010
[MA000020]

Building, metal and civil construction industries

JUSTICE ROSS, PRESIDENT
VICE PRESIDENT CATANZARITI
COMMISSIONER HAMPTON

MELBOURNE, 31 OCTOBER 2020

Expense-related allowances.

A. Pursuant to s.157 of the Fair Work Act 2009, the above award is varied as follows:

1. By deleting the table appearing in clause 20.1(a) and inserting the following:

.

Classification

Tool allowance
$ per week

Artificial stoneworker, carpenter and/or joiner, carpenter-diver, carver, bridge and wharf carpenter, floor sander, letter cutter, marble and slate worker, stonemason or tilelayer

32.70

Caster, fixer, floorlayer specialist or plasterer

27.04

Refractory bricklayer or bricklayer

23.21

Roof tiler, slate-ridger or roof fixer, tradespersons in the metals and engineering construction sector

17.13

Signwriter, painter or glazier

7.85

2. By deleting the amount “$15.38” appearing in clause 20.2(a) and inserting “$15.71”.

3. By deleting the amount “$15.38” appearing in clause 20.2(c) and inserting “$15.71”.

4. By deleting the amount “$1862” appearing in clause 20.3(b) and inserting “$1896”.

5. By deleting the amount “$72.02” appearing in clause 24.3(a)(i) and inserting “$73.47”.

6. By deleting the amounts “$203.61” and “$29.06” appearing in clause 24.4(b) and inserting “$205.14” and “$29.28” respectively.

7. By deleting the amount “$15.38” appearing in clause 24.6(a)(i) and inserting “$15.71”.

B. This determination comes into operation on 1 November 2020. In accordance with s.165(3) of the Fair Work Act 2009 this determination does not take effect in relation to a particular employee until the start of the employee’s first full pay period that starts on or after 1 November 2020.

PRESIDENT